Risk Ranking Analysis
Process
The
following Risk Ranking Analysis Process uses typical Severity, Likelihood, and
Risk Rating definitions. The definitions
and values are usually set by the individual company, can vary greatly from one
company to another, and are a direct reflection of the company's tolerance to
risk.
1.
Rate
the Severity of the potential fall hazard using to the typical Severity
Definitions chart.
Typical Severity
Definitions
|
1
- Very high |
-
Fatality |
|
2
- High |
-
Lost Time Injury |
|
3
- Medium |
-
OSHA Recordable Injury |
|
4
- Low |
-
First Aid Injury |
|
5
- Very Low |
-
No worker injuries |
Typical
Likelihood Definitions
|
1
- Very high |
Possible
to occur frequently (1/year) |
|
2
- High |
Possible
to occur occasionally (1/5 years) |
|
3
- Medium |
Possible
to occur under unusual circumstances (1/15 years) |
|
4
- Low |
Possible
to occur over the lifetime of the facility (1/30 years) |
|
5
- Very Low |
Could
occur however not likely over facility life (1/100 years) |
3.
Determine
the Risk Rating of the fall hazard from the following Typical Risk Ratings. The combination of the various levels of
severity and likelihood is then given a ranking which corresponds to the risk
of each individual scenario. The levels
chosen for the matrix are an indicator of the employer’s risk tolerance.
Typical Risk Ratings
SEVERITY
|
Likelihood |
1 |
2 |
3 |
4 |
5 |
|
1 |
1 |
2 |
3 |
4 |
7 |
|
2 |
2 |
4 |
6 |
7 |
8 |
|
3 |
3 |
6 |
7 |
8 |
9 |
|
4 |
4 |
6 |
8 |
9 |
10 |
|
5 |
7 |
8 |
9 |
10 |
10 |
Some
employers have set up a priority system based solely on the resulting ranking.
For example, they have set a priority as shown below:
Sample
Decision-Making Rules for Risk Ranking
|
Ranking
Levels |
Description |
Action
Required |
|
1 |
Very
High |
Must
be mitigated with engineering and administrative controls before continued
operation |
|
2
or 3 |
High |
Must
be mitigated by engineering controls within six months |
|
4 |
Medium |
Must
be mitigated by administrative controls within six months |
|
5
or 6 |
Low |
Mitigation
is optional depending on cost-benefit |
|
7 |
Very
Low |
No
mitigation required |
Generally,
risk levels of 7 or better are low in priority for improvement. Risk levels of 1, 2 or 3, would suggest some
urgency be reflected in the recommendation follow-up plan.
The
analysis team may find that it is useful to also rank the severity and likelihood
of outcomes from implementing the recommendations. If multiple recommendations yield similar
risk ratings, then the project team may choose to implement the recommendations
according to cost, ease of implementation, or other business criteria.